Forensic schedule and delay analysis
When a milestone moves, the question is which activity moved it and through which logic. The analysis traces the driving path backward relationship by relationship and compares each update with the one before.

Problems this solves
- A key milestone slipped between updates and the cause is disputed.
- Several activities moved at once and it is unclear which one drives the milestone.
- Near-critical paths may take over once the critical path is recovered.
- A recovery proposal needs to show its effect through the whole network.
What the work covers
Slip analysis
Activities matched by Activity ID across updates, ranked by finish movement, with the field that changed.
Driving-path tracing
The predecessor with the least relationship float at each step, with relationship type, lag and dates shown as evidence.
Near-driving paths
Relationships within a set number of days of driving, so a second path is not missed.
Recovery scenarios
A proposed change scheduled through the network and the milestone re-forecast from the result.
Typical deliverables
- Slip register by update with the activities that moved
- Driving path from the milestone to its first open driver
- Relationship evidence: type, lag and relationship float
- Recovery scenario and its re-forecast milestone
This work supports project teams and their advisers. McKowen Project Controls does not provide legal opinions or expert-witness testimony.
How the work runs
- Collect the updates in order. Each schedule update identified by its data date, so every comparison is between consecutive snapshots.
- Find what moved. Activities matched by Activity ID; finish movement ranked by update and against the original baseline.
- Trace the cause. The driving path from the late milestone back to its first open driver, with the relationship evidence.
- Test recovery options. Each option scheduled through the network, with the milestone it recovers and by how much.
See a working demonstration
Each demonstration opens on the home page with a fictional project and synthetic data. Sort, filter and drill into the records.
- Open the Logic Tracer demonstrationSelect a milestone and trace its driving path backward relationship by relationship: path order, logic map and Gantt views…
- Open the Forensic Slip Analysis demonstrationFinds where the schedule moved between updates and against the baseline, ranks the largest slips and pulls, and shows which…
- Open the Delay Consequence Ranking demonstrationGives every open activity the same slip, recalculates the schedule and ranks activities by the milestones they would move…
- Open the Update-to-Update Trend demonstrationMilestone forecasts for all twelve updates side by side, with critical and negative-float counts; activity-level movement for the…
Watch it working
A narrated screen recording of the Logic Tracer on a synthetic schedule: a late milestone traced back to its driving activity, the logic map, near-driving paths, the Gantt view and a recovery scenario. Fictional project, synthetic data.
Read the transcript
This is the Logic Tracer, shown on a synthetic schedule, presented by McKowen Project Controls.
Ready for Start-up is selected. Its current forecast, BL2, is thirty September twenty twenty-six: seven working days later than the previous update, and twelve later than the original baseline.
Trace path walks backward through the current update. At each step it keeps the open predecessor with the least relationship float. Nine activities drive this milestone.
The first open activity on the path is the residue gas compressor delivery, P twenty fifty. Its finish moved from twenty March to three April: ten working days later than the previous update, and fifteen later than the baseline. It drives C thirty-two forty through a finish-to-start link with zero relationship float, and its total float is minus twelve days.
The path order table lists every step with its baseline, previous and current dates, the three variances, and the link each activity drives through.
Near-driving links look for any relationship within ten days of driving. There are none in this update, so this single path sets the date.
The Gantt view lines the path up against the original baseline, the previous update, and the data date.
Finally, a hypothetical recovery, labeled as a scenario and not the approved schedule. The hydrotest is re-sequenced from thirty-two to twenty-nine working days, and the whole network is rescheduled. Ready for Start-up moves to twenty-five September: three working days earlier.
Explore the Logic Tracer yourself on the website.
See it on your own schedule
A live demonstration walks through this work with you, on the reports above or on your own schedule export.
Questions clients ask
Do you provide expert-witness testimony?
No. The work is schedule analysis that supports the project team and its advisers: what moved, when, and which logic drove it. Legal opinions and expert testimony are outside the scope.
How is the driver of a late milestone found?
The driving path is traced backward from the milestone relationship by relationship, keeping at each step the predecessor with the least relationship float, and compared across the baseline and each update.
Can you work from updates we already have?
Yes. The analysis uses the baseline and the sequence of updates the project holds, matched by Activity ID.