Home / Project controls glossary

Project controls glossary

Plain definitions of the scheduling terms used across this site, including how BL, BL1 and BL2 and the three variances are calculated.

Baseline BL1 BL2 Prior Period Variance Current Period Variance Period-over-Period Variance Data date Total float Relationship float Driving path Near-driving path Critical path Open end Hard constraint Lag Out-of-sequence progress DCMA 14-point assessment Look-ahead Ready to Start Level One schedule Construction work package 4D model Mechanical completion Ready for start-up

Baseline (BL)
The locked original approved schedule. Every later update is measured against it.
BL1
The previous reporting update. On this site, update 11 with a data date of 20-Oct-25.
BL2
The current reporting update. On this site, update 12 with a data date of 17-Nov-25.
Prior Period Variance
BL finish minus BL1 finish, in working days. Negative means the previous update was later than the baseline.
Current Period Variance
BL finish minus BL2 finish, in working days. Negative means the current update is later than the baseline.
Period-over-Period Variance (PoP)
BL1 finish minus BL2 finish, in working days: how far a date moved in this reporting period. Negative means it moved later.
Data date
The date up to which progress is recorded. Actual dates fall before it and forecast dates after it.
Total float
How far an activity can slip before it delays the project finish or a constrained milestone. Negative total float means the schedule already misses that date.
Relationship float
The slack on one logic link between two activities. The driving predecessor is the one whose link has the least relationship float.
Driving path
The chain of activities, linked with the least relationship float, that sets the date of a milestone. Tracing it backward finds the cause of a slip.
Near-driving path
A path whose links are within a few working days of driving. A small slip there can make it the driving path.
Critical path
The longest path through the schedule, with the least total float. A delay on it delays the finish.
Open end
An activity with no predecessor or no successor. Open ends break the logic and hide the real critical path.
Hard constraint
A date fixed on an activity that overrides its logic. Used only where a contract date requires it.
Lag
A delay applied to a relationship. Long lags hide work that should be its own activity.
Out-of-sequence progress
Work recorded as started before its predecessors allow under the schedule logic.
DCMA 14-point assessment
A set of fourteen schedule quality checks covering logic, leads, lags, relationship types, constraints, float, duration, resources, missed tasks and the critical path.
Look-ahead
A list of activities due in the coming weeks, usually two, four or twelve, with predecessor status.
Ready to Start
Activities whose predecessors are complete, so the field can start them. Previous week plus added minus cleared equals current.
Level One schedule
A one-page schedule of the project's major phases and milestones for leadership review.
Construction work package (CWP)
A defined portion of construction scope, usually by area and discipline, used to plan and sequence the work.
4D model
A 3D model whose objects are linked to schedule activities, so construction can be shown at any date.
Mechanical completion
The milestone at which construction of a system is complete and it is ready for pre-commissioning.
Ready for start-up (RFSU)
The milestone at which commissioned systems are ready to introduce process fluids and start up.

See the terms working

Every term above is used in the reporting demonstrations and the 4D model, on a fictional project with synthetic data.